2018 end of year update
News Articles | 21 December 2018

2018 end of year update

Tunnel boring machine (TBM) Grace has been very busy in 2018 reaching the halfway mark (3571m) of her underground journey in November, and clearing the airside environment in December.

November 2018 update
News Articles | 19 November 2018

November 2018 update

November has seen a high volume of concrete works taking place across our construction sites.

October 2018 update
News Articles | 25 October 2018

October 2018 update

TBM Grace has made good progress in the last month and has now tunnelled 44 per cent of the entire tunnel length between Forrestfield and Bayswater Junction.

September 2018 update
News Articles | 14 September 2018

September 2018 update

Earlier this month both tunnel boring machines (TBMs) reached another milestone, having now built a third of the entire length of the tunnels between Forrestfield and Bayswater Junction.

August 2018 update
News Articles | 20 August 2018

August 2018 update

After leaving the Airport Central Station box in June, tunnel boring machine (TBM) Grace has hit another milestone tunnelling a total of 2.5km from the dive structure in Forrestfield.

July 2018 update
News Articles | 26 July 2018

July 2018 update

In another exciting project milestone, both TBMs have now left Airport Central Station to tunnel the 2.8km towards Redcliffe Station.

June 2018 update
News Articles | 15 June 2018

June 2018 update

Following TBM Grace’s arrival at Airport Central Station on May 8, TBM Sandy also broke though into the station’s underground box late last month.

May 2018 update
News Articles | 11 May 2018

May 2018 update

In one of the project's biggest milestones to date, TBM Grace broke through into the underground station box at Airport Central Station on the evening of Tuesday May 8, 2018.

April 2018 update
News Articles | 19 April 2018

April 2018 update

TBM Grace resumed tunnelling this month and has now successfully installed 1034 rings. The restart follows the completion of a comprehensive review into tunnelling operations.

March 2018 update
News Articles | 13 March 2018

March 2018 update

As we progress towards first trains using the Forrestfield Line in 2020, key infrastructure along the new alignment, including all three new stations, is now well into construction.

RSS
123456789


Media enquiries about the Forrestfield-Airport Link can be directed to the Public Transport Authority:
Media line: (08) 9326 2526
Email: media@pta.wa.gov.au
Please note emails are monitored Monday to Friday, 9am to 5pm AWST.

Media enquiries from students must be sent from school or university email accounts.