March 2019 update
News Articles | 11 March 2019

March 2019 update

Concrete has been the big ticket item in the past month with slab pours taking place left, right and centre. A lot of construction work has become more visible now with above-ground structures starting to take shape across several of the sites.

February 2019 update
News Articles | 7 February 2019

February 2019 update

It has been a busy start to 2019, with works continuing across nine construction sites, our stations starting to take shape, segment production reaching 91 per cent and the tunnel boring machines (TBMs) beginning their ascent towards Redcliffe Station.

2018 end of year update
News Articles | 21 December 2018

2018 end of year update

Tunnel boring machine (TBM) Grace has been very busy in 2018 reaching the halfway mark (3571m) of her underground journey in November, and clearing the airside environment in December.

November 2018 update
News Articles | 19 November 2018

November 2018 update

November has seen a high volume of concrete works taking place across our construction sites.

October 2018 update
News Articles | 25 October 2018

October 2018 update

TBM Grace has made good progress in the last month and has now tunnelled 44 per cent of the entire tunnel length between Forrestfield and Bayswater Junction.

RSS
12345678910Last


Media enquiries about the Forrestfield-Airport Link can be directed to the Public Transport Authority:
Media line: (08) 9326 2526
Email: media@pta.wa.gov.au
Please note emails are monitored Monday to Friday, 9am to 5pm AWST.

Media enquiries from students must be sent from school or university email accounts.