January 2017 update
News Articles, Monthly Updates | 18 January 2017

January 2017 update

With the arrival of the tunnel boring machines and all four major construction sites becoming operational in 2017, this year will be our busiest yet.

2016 end of year update
News Articles, Monthly Updates | 16 December 2016

2016 end of year update

This year has seen the project shift into construction phase, with SI-NRW awarded the major design and construct contract in April and starting construction works in November.

October 2016 update
News Articles, Monthly Updates | 31 October 2016

October 2016 update

The development application for Early Works at Forrestfield was approved this month and as a result preparation for the construction of key infrastructure has now started.

September 2016 update
News Articles, Monthly Updates | 7 October 2016

September 2016 update

Works are now underway to establish the construction site at Forrestfield. This is the first step in preparing for the arrival of the tunnel boring machines (TBMs) mid next year.

August 2016 update
News Articles, Monthly Updates | 5 September 2016

August 2016 update

There has been a hive of activity across the entire project footprint this month with site investigations conducted, final designs being progressed and PTA’s forward works continuing as planned.